Tuesday 26 January 2016

Production Schedule #4


Jan 9 (12 to 1 O'clock)
Zombie opening scene practice shoots. Shots 1-2 (DONE)
Jan 10 (12 to 4 O'clock)
Practice shoots every shot with main actor try costume. Shots 3-32 (DONE)
Jan 17 (12 to 5 O'clock)
Shoot title sequence where main character kills animal. (DONE)  
Jan 30 (12 to 4 O’clock)
Film all shots with field and car.
Jan 31 (12 to 2 O’clock)
If needed film the rest of the needed shots.

Instead of filming on Jan 23 and 24 i will be filming on the 30 and 31. 

No comments:

Post a Comment

All comments will be moderated before being posted.